Compliance report
The compliance report is the evidence file for an audit: for a period, every merge request handled under change management with its policy, decision, approval, scans and merge, the changes that reached a branch under change management without a merge request, the company's audit trail and a summary of background jobs. It is downloaded as a CSV or a PDF file.
Who may export it
Platform admins, company admins and auditors (the roles that read the audit log). Policy managers and users cannot. A platform admin exports the report of the company selected in the header.
Exporting it
Audit log → Export report, then Download. The panel and its settings (From, To, Changes, Format) are described in Audit log → Export report.
- Period: whole days in the company's time zone (company General tab; UTC when it is not set), the end day included. By default the last 30 days.
- Changes: Merged in the period (the default) covers the merge requests merged between the two dates; Opened in the period those opened between them (on the VCS; when the VCS did not say, when Merge Pilot first recorded them).
- Format: CSV or PDF.
The download is named compliance-report-<company>-<from>-to-<to>.csv (or .pdf). When a part was cut at its limit, the page says Report truncated and names each part cut, for example Audit entries: 5,000 of 6,120 included. Use a shorter date range for complete data. (the parts are Merge requests, Audit entries and Changes outside change management); otherwise Report downloaded successfully.
What is in it
Merge requests
The merge requests of the company in the period, oldest first, that were under change management:
- merge requests of watched repositories are left out (the monitoring report covers them), except one that merged without approval while under change management;
- merge requests imported from a watched repository's history are left out.
Changes outside change management
Direct changes found in the period on branches of repositories under change management, oldest first. Changes to watched repositories are not in it. Nothing is listed when the company does not record direct changes.
Audit trail
The company's audit log entries of the period, oldest first: time, user name, action, resource, resource ID, result and IP address. Platform entries (those of no company) are not in it. The actions are listed in Audit log → Audit actions.
Job processing summary
The company's background jobs created in the period, per job type: total, completed and failed. See Jobs.
Limits
| Format | Merge requests | Changes outside change management | Audit entries |
|---|---|---|---|
| CSV | 10,000 | 10,000 | 10,000 |
| 2,000 | 2,000 | 5,000 |
The first entries of the period, oldest first, are kept. A part that was cut says so in the file.
The CSV file
The file starts with a byte-order mark so spreadsheets read it as UTF-8. A value that starts with =, +, -, @, a tab or a carriage return (a title, an author, a branch name, a commit title, anything the report's data fills in) is prefixed with ' so spreadsheets do not read it as a formula. Times are in the company's time zone, with the zone's name (2026-10-26 14:05:00 CET). Yes/no columns are true or false. It holds, one after the other, separated by an empty row:
Header: === Compliance Evidence Report ===, then Company, Period, Period applies to (merge date or opening date), Generated, Generated By, and a Note for each part that was cut (MR data truncated: N of M records included).
=== Merge Request Evidence (N records) ===, one row per merge request:
| Column | Shows |
|---|---|
| Repo | The repository's ID on the VCS |
| MR#, Title, Author | As on the VCS |
| Source Branch, Target Branch | Its branches |
| State | opened, merged, closed or out_of_scope |
| Opened | When it was opened on the VCS (when the VCS did not say, when Merge Pilot first recorded it) |
| Merged At, Merged By | When and by whom it merged |
| Merged Commit | The merge request's head commit when it merged |
| Approved Commit | The head commit the approved change approval covered (empty unless the change approval is approved) |
| Merged Commit Approved | true when the merged commit is the approved one |
| Separation Of Duties | The separation-of-duties exceptions noted on the merge request, separated by ; |
| SoD Violation | true when a policy that forbids it saw an approver merge the merge request |
| Merged In Freeze | The name of the change freeze it merged in, against it |
| Approval Revoked After Merge | true when the change approval's approval was withdrawn in the tracker after the merge |
| Policy, Policy Version | The policy that covered it and the version |
| Change Type | standard, normal or emergency |
| Priority | The policy's priority |
| Gate | The merge gate: approved, pending or blocked |
| Gate Commit | The head commit the decision was made for |
| Open Controls | Each enforced control that did not pass, as control (status): reason, separated by ; |
| Merged Without Approval | true when it merged although change management had not approved it |
| Review Due | For an emergency change, when its review is due |
| Risk Level, Risk Score | The risk assessment (score with one decimal) |
| In Blackout | true when the risk assessment found it in a change freeze |
| Risk Held | true when the risk check held it |
| Change Approval Key, Change Approval Status | Its change approval and status |
| Earlier change approvals | How many earlier change approvals it had (superseded or reopened) |
| Approved, Approved By, Approved At | The approval |
| Votes | Each vote as voter decision (source), separated by ; |
| Secret Scan, Secrets Found | The secret scan's status and the number of possible secrets |
| Dependency Scan, New Vulnerabilities, Highest Severity | The dependency scan's status, the vulnerabilities the merge request brings in, and the highest severity |
| Pipeline Status, Pipeline ID | The latest pipeline recorded on it |
=== Changes Outside Change Management (N records) ===, one row per direct change: Detected, Repo (the project's path), Branch, Pushed By, Found By (push or head_check), Force Push, Branch Deleted, Commits, Commits Without MR, Before, After (the branch head before and after) and Commit Titles (of the commits not from a merge request, separated by |).
=== Audit Trail (N records) ===: Timestamp, Username, Action, Resource, Resource ID, Status, IP.
=== Job Processing Summary ===: Type, Total, Completed, Failed.
The PDF file
A landscape A4 document with Page N of M and the generation time on every page:
- First page: Compliance Evidence Report, the company, the period, and who generated it when, then the Summary: the total merge requests, a risk breakdown (low, medium, high, critical) of the merge requests included, the changes outside change management, the total audit entries, the job success rate (completed of all jobs), and a note for each part that was cut.
- Merge Request Evidence: Repo, MR#, State, Author, Policy (name and version), Change, Gate, Risk, Change Approval Key, Change Approval Status, Approved By, Secrets (the scan status, or N found), Pipeline and Merged (the date). Long values are shortened with ..., by characters (a letter such as ş or ü is never cut in half). The Gate column flags merges the gate did not cover, in this order: BYPASSED (merged without approval), SOD BROKEN (separation of duties broken), IN FREEZE (merged in a change freeze), REVOKED (approval withdrawn after the merge); otherwise the gate.
- Changes Outside Change Management: Detected, Repo, Branch, Pushed By, Found By, Forced, Deleted, No MR (commits without a merge request of all commits) and After.
- Audit Trail and Job Processing Summary, with the CSV's columns.
An empty part says so (No merge request records found for this period., No change reached a branch under change management without a merge request in this period., No audit log records found for this period., No job records found for this period.).
Audit
Every export is recorded as compliance_export (resource report): on success with the format, the period, the number of merge requests, audit entries and changes outside change management included and in total, and whether each was cut; on failure with the error. See Audit log.
API
GET /api/v1/compliance/report streams the file.
| Parameter | Values |
|---|---|
format | csv (the default) or pdf |
from, to | YYYY-MM-DD (days in the company's time zone, to included) or RFC 3339 times. By default the last 30 days |
date_basis | merged_at (the default) or opened_at |
company_id | Platform admins only, required for them |
The answer's headers say what was included: X-Report-Truncated names the parts that were cut, comma-separated (merge_requests, audit_entries, direct_changes; empty when none was), and each part has its total and the number included: X-Report-Total-MRs and X-Report-Returned-MRs, X-Report-Total-Audit-Entries and X-Report-Returned-Audit-Entries, X-Report-Total-Direct-Changes and X-Report-Returned-Direct-Changes.
Policy managers and users get 403; a platform admin without company_id gets 400; a wrong format, date_basis or date gets 400.
Related pages
- Audit log: the export panel and every audit action.
- Direct changes.
- Monitoring report: the evidence of watched repositories.
- Merge gate.
Video tutorial